11376-2026
Construction Clausura
Municipalidad de Nicoya - Departamento de Control Constructivo
RESOLVED - Won
Case Information
Authority
Arq. Cesar Andres Espinoza Diaz (Coordinator)
Property
Finca 5370-M-000
Filed
April 21, 2026
Resolved
June 3, 2026
Resolution Details
MN-DPTSA-CCOP-RES-006-06-2026
First
Original clausura action was legal and based on official Direccion de Aguas info
Second
Revocatoria GRANTED - water system operability proven during proceedings
Third
CLAUSURA LIFTED - construction can resume
Fourth
Apelacion declared MOOT since revocatoria granted
Timeline
Mar 12, 2026
Direccion de Aguas sends oficio about pozo CJ-135
Apr 16, 2026
Muni orders clausura preventiva (NOT-055-03-2026)
Apr 21, 2026
Marion files recurso de revocatoria
May 2026
INVU opinion - administrado should have chance to prove
May 6, 2026
Muni inspection confirms water system operational
Jun 3, 2026
Resolution issued - clausura lifted
Jun 5, 2026
Formal inspection to lift clausura completed
Key Evidence
Inspection findings (May 6, 2026):
INVU Opinion (CDU-212-05-2026):
Concession alone not sufficient if source not operational, BUT administrado should have opportunity to rehabilitate or prove alternative source.
- Pozo CJ-135: Operational with pump + electrical system
- Storage tank: 155,000L capacity in place
- Distribution: Network reaching all lots
- Concession: Valid through 2036
INVU Opinion (CDU-212-05-2026):
Concession alone not sufficient if source not operational, BUT administrado should have opportunity to rehabilitate or prove alternative source.